Golden Eagle Road Completion Update

Post Date:09/06/2017 2:43 PM

The dirt extension of Golden Eagle Rd in the Skyline Ridge/Kiowa Valley area is in the process of being constructed and paved. Following is information regarding the timeline for completion for this project.

The developer of the Skyline Ridge area contracted with Salt Lake Excavating to pave the extension of Golden Eagle Road. The original deadline from the City was August 31 in order to have the City reimburse costs for the project in the amount of $100,000. This $100,000 was intended to incentivize this project to be done in 2017 rather than sometime in the future when development would mandate its completion.

However, during the course of excavation it was discovered that a water line that had been installed years ago was too shallow for the paving to occur without the line being buried lower. City staff and representatives of the developer have been in contact with one another to address this issue. Throughout these discussions, it has become apparent the delay was not caused by either the developer or the excavator and the correction was necessary to avoid problems later. As this was not the developer’s or excavator’s fault, the City has agreed to extend the deadline for paving until October 2, 2017 to compensate for the delays created by the water line repair.

We apologize for any inconvenience this has caused and appreciate your patience while this project is completed.