Redwood Road Construction Updates

Post Date:08/09/2017 3:18 PM

 

Redwood Road Madimimi Banner-01

Update - October 13, 2017

 

New Traffic Patterns Upcoming on Redwood Road

As part of road widening efforts, crews will begin demolition activities on the east side of Redwood Road as early as next week. Traffic shifts to the west side of the road will begin to allow room for work. Drivers should be aware of new traffic patterns and drive cautiously.

 

1

Milled roadway ready for asphalt paving - north of Tanner Lane

 

5

Compacting base materials - north of Lake View Terrace Road

 

WIDENING: 400 South to Lake View Terrace Road

 

Redwood Road: Asphalt paving from 400 South to Grandview Boulevard will begin this weekend. Placement of road base materials continues near Lake View Terrace Road. Signal work at Grandview Boulevard is underway as crews install the signal poles.

 

4

Drainage work - south of Lake View Terrace Road

Grandview Boulevard and Lake View Terrace Road:
Utility and drainage work is ongoing. Asphalt paving may begin as early as this weekend. Pedestrians should avoid construction areas.

 

2

Completed sidewalk and curb and gutter - Grandview Boulevard

 

RESURFACING: Village Parkway south, approximately 10 miles

Project Nearing Completion

Minor construction activities are taking place as crews work on final details of the project. Beginning mid- to late October, a guardrail will be installed near mile marker 21 (about four miles south of Harbor Parkway). One-way flagging will be used during this operation to allow room for work.

If you have any questions, contact a project representative at 801-997-5682 or redwoodsaratoga@utah.gov.

 

FullSizeRender

Resurfacing project nearing completion

 

WIDENING

Upcoming Work

▪Next week: New traffic patterns begin
▪Roadway demolition and utility work at 400 South

Next week: New traffic patterns begin

 

Roadway demolition and utility work at 400 South

Ongoing Work

▪Roadway excavation
▪Roadway reconstruction
▪Asphalt paving
▪Curb and gutter installation
▪Utility work
▪Drainage work
▪Traffic signal foundation installation at Grandview Boulevard
▪Grandview Boulevard and Lake View Terrace Road: Roadway reconstruction, utility work, curb and gutter installation, and sidewalk and pedestrian ramp reconstruction

Roadway excavation

 

Roadway reconstruction

 

Asphalt paving

 

Curb and gutter installation

 

Utility work

 

Drainage work

 

Traffic signal foundation installation at Grandview Boulevard

 

Grandview Boulevard and Lake View Terrace Road: Roadway reconstruction, utility work, curb and gutter installation, and sidewalk and pedestrian ramp reconstruction

 

RESURFACING

Upcoming Work

▪Guardrail installation

Guardrail installation

Ongoing Work

▪Shoulder work
▪Project area clean up

Shoulder work

 

Project area clean up

 

***

 

Hours of Operation

Daytime Hours
Monday to Saturday (Sundays as needed)
6 a.m. to 7 p.m.

Nighttime Hours
Sunday to Friday (Saturdays as needed)
6 p.m. to 7 a.m.

Construction activities and schedule are weather- and equipment-dependent and subject to change.

 

What to Expect During Construction

▪Noise
▪Dust
▪Vibration
▪One-way flagging
▪Uneven lanes
▪Traffic delays
▪Lane shifts
▪Steel plates on roadway
▪Reduced speed limits
▪Trucks entering/exiting work zone

Noise

 

Dust

 

Vibration

 

One-way flagging

 

Uneven lanes

 

Traffic delays

 

 

 

Contact Us

Please contact a member of our team if you have any questions.

801-997-5682
redwoodsaratoga@utah.gov
udot.utah.gov/redwoodsaratoga