Redwood Road Construction Updates

Post Date:08/09/2017 3:18 PM

Update - August 18, 2017

 

Additional congestion expected next week

School begins on August 22, which means traffic will increase, especially during peak commute hours and sporting events at the high school. We encourage residents to implement the following items to help decrease congestion during the school year:

▪Walk or bike to school when possible.
▪Ride the bus if provided.
▪Organize a carpool in your neighborhood.
▪Watch for school buses and give them time and space for left turns.

Walk or bike to school when possible.

 

Ride the bus if provided.

 

Organize a carpool in your neighborhood.

 

Watch for school buses and give them time and space for left turns.

For parents: Visit UDOT's Student Neighborhood Access Program (SNAP) website to learn about walking and biking safely to and from school.

For drivers: Visit UDOT’s TravelWise website for strategies to plan ahead and reduce trips, which will result in fewer delays during construction on Redwood Road.

 

IMG 1231 - south of Grandview

Road reconstruction south of Grandview Blvd.

 

WIDENING: 400 South to Lake View Terrace Road

Crews are relocating utilities in conjunction with road reconstruction on the west side of Redwood Road. Signal work at the Grandview Boulevard intersection will begin as early as next week.

 

IMG 1224

Compacting road in preparation for paving on Lake View Terrace Road

Grandview Boulevard and Lake View Terrace Road: Asphalt paving will begin on Friday, Aug. 18. Traffic will be shifted to the middle lanes as early as next week. Sidewalks and crosswalks on Grandview Boulevard will be closed for up to two more weeks while crews reconstruct pedestrian ramps.

 

RESURFACING: Village Parkway south, approximately 10 miles

Night work schedule

▪Nighttime paving operations from Harbor Parkway to Village Parkway should be complete by early next week.
▪Crews will continue night work, and will work from Harbor Parkway to the south for about eight miles.
September 5: Crews plan to switch back to daytime hours to continue paving operations.

Nighttime paving operations from Harbor Parkway to Village Parkway should be complete by early next week.

 

Crews will continue night work, and will work from Harbor Parkway to the south for about eight miles.

 

September 5: Crews plan to switch back to daytime hours to continue paving operations.

Residents can expect noise, dust, vibrations, and construction lighting. Drivers should expect uneven lanes, reduced speed limits, one-way flagging, stopped traffic, and delays in this area. Construction activities and schedule are weather dependent.

If you have any questions, contact a project representative at 801-997-5682 or redwoodsaratoga@utah.gov.

 

IMG 1261

Seam between existing road and newly paved road

 

WIDENING

Upcoming Work

Next week: Pour concrete foundations for traffic signal at Grandview Boulevard intersection
Next week: Lane shifts on Grandview Boulevard and Lake View Terrace Road

Next week: Pour concrete foundations for traffic signal at Grandview Boulevard intersection

 

Next week: Lane shifts on Grandview Boulevard and Lake View Terrace Road

Ongoing Work

▪Asphalt removal
▪Utility and drainage work
▪Roadway reconstruction
Grandview Boulevard: Asphalt paving, utility work, and roadway/pedestrian ramp reconstruction
Lake View Terrace Road: Asphalt paving, utility work, and roadway reconstruction

Asphalt removal

 

Utility and drainage work

 

Roadway reconstruction

 

Grandview Boulevard: Asphalt paving, utility work, and roadway/pedestrian ramp reconstruction

 

Lake View Terrace Road: Asphalt paving, utility work, and roadway reconstruction

 

RESURFACING

Upcoming Work

▪Asphalt removal and paving south of Harbor Parkway
▪Asphalt paving on widened shoulders
▪Microsurfacing (adding a protective layer to the newly paved road)

Asphalt removal and paving south of Harbor Parkway

 

Asphalt paving on widened shoulders

 

Microsurfacing (adding a protective layer to the newly paved road)

Ongoing Work

Harbor Parkway to Village Parkway: Asphalt removal and paving

Harbor Parkway to Village Parkway: Asphalt removal and paving

Other Projects in the Area

Please be aware that Saratoga Springs City is doing utility work on Redwood Road near Pioneer Crossing.

 

IMG 1215 - black pipes

(Left and right) Utility materials

 

IMG 1219 - cement pipe

 

Hours of Operation

Daytime Hours
Monday to Saturday (Sundays as needed)
7 a.m. to 7 p.m.

Nighttime Hours
Sunday to Friday (Saturdays as needed)
6 p.m. to 7 a.m.

Construction schedules are weather-dependent and subject to change.

 

What to Expect During Construction

▪Noise
▪Dust
▪Vibration
▪Construction lighting
▪One-way flagging
▪Uneven lanes
▪Traffic delays
▪Lane shifts
▪Reduced speed limits
▪Trucks entering/exiting work zone